ROM ±25% 2026 dollars · Mountain-West rural · Site prep excluded

Budget Analysis vs $1.75M

Summary

The design as written rolls up to ~$2.13M before site prep at the likely-case midpoint (original waterfall figure). With Peter's flooring LDD-FINISH-01 added (~$70K, missing from the original set), the updated total lands at ~$2.43M.

ScenarioTotalvs $1.75M
Low case (favorable bids + everything goes right)~$1.85M+$100K (6%) over
Likely case (recommended planning number)~$2.43M+$680K (39%) over
High case (bid market + change orders)~$2.75M+$1.0M (57%) over

Add site prep (builder estimate ~$50K, but with wide uncertainty) and the gap grows by that amount.

Bottom line

The $1.75M strict budget is not achievable with the design as written. Three possible paths:
  1. Grow the budget to $2.0–2.2M plus site prep (most honest reading).
  2. Cut $300–400K of scope — see "Cost-reduction levers" below.
  3. Phase the build — defer LOW finish, defer one ILS bay, defer lift to Phase 2.

Budget waterfall

Budget waterfall showing ROM cost stack vs $1.75M envelope
Original waterfall shows $2.13M; add ~$70K for Peter's LDD-24 flooring to reach ~$2.43M total.

Line-item rollup (likely case)

Category$K likely$K rangeNotes
Foundation + slab130100–160Includes radiant + slab-edge insulation. Site prep excluded.
PEMB shell + erect220180–2604-bay × 30' frame package, erection included.
Exterior envelope (IMP walls)230190–2804" PVDF tier; lower tier saves $20–40K.
Roof IMP + drainage9070–110Separate from wall IMP.
Spine wall + glazing11080–140Includes 18'×10' glass garage door.
Gym hero wall + clerestory7055–95~190 sqft of clerestory.
Interior framing + drywall9575–125Habitable-zone assemblies.
HVAC175130–225Ducted + mini-splits + ERV.
Radiant + manifolds10585–1353 clusters; gypcrete upstairs.
Plumbing + fixtures11590–150DWV + supply + 7 toilets + 10 sinks.
Electrical + EV + solar-ready11090–140400A + 2 subpanels.
Lighting (soffit + scene)7055–95Linear LED + Lutron.
Doors + stairs + finish11085–14530+ doors, 54" stair.
Kitchen + cooking + island vent9570–130Custom integrated system.
Workshop + lift + equipment9570–135Lift dominates.
ILS finish + appliances8565–115Aging-in-place fixtures.
Flooring + threshold (LDD-24, new)7050–95Gym urethane + SPC LVP + polished concrete + flush threshold.
Permits + design + GC fee130100–170~6–8% GC fee.
Subtotal hard + soft2,2051,790–2,800
Contingency 10%220
Project total~2,425~$2.0M–$2.7MBefore site prep.

Cost-reduction levers

Easy wins (do these first)

MoveSavingsCost
Downgrade IMP exterior finish tier (PVDF → SMP polyester)$20–40KFaster fade in 10–15 years
Defer LOW finish and fixtures to Phase 2 (rough-in only)$40–80KLOW unusable until Phase 2
Defer one ILS bedroom or bathroom finish$30–60KLess ILS flexibility
Heat-pump water heater instead of distributed tankless$5–15KSlightly less flow capacity
Vinyl LVP instead of luxury SPC$10–20KFloor-feel + warranty considerations
Single washer/dryer set instead of two$5–10KLess laundry capacity
Standard sectional garage doors$5–10KAesthetic compromise on south face

Easy-win subtotal: $115–235K. Possibly enough to close half the gap.

Harder cuts (more political)

MoveSavingsCost
Defer or eliminate lift$25–55KLOW access via stair only; not aging-in-place
Standard hanging hood instead of LDD-07 integrated vent$25–60KBig aesthetic compromise over kitchen
Dry climate-panel radiant upstairs instead of gypcrete$10–25KWorse acoustics + slower response
Eliminate destratification fans$20–35KGym comfort worse in winter
Reduce service to 300A from 400A$4–8KTight on long-term capacity

Hard-cut subtotal: up to $85–186K saved, but each cuts the design's identity.

Recommended path

Reviewer recommendation

  1. Confirm with the builder/owner: is $1.75M strict, or is there 10–15% headroom?
  2. Get site prep from civil engineer next week. Without it, every other number floats.
  3. If $1.75M is strict and site prep is ~$50K: easy wins + defer LOW gets you to ~$2.0M before site prep — still over, but much closer. The remaining $200–250K gap probably means cutting an identity item or accepting a moderate overrun.
  4. If $1.75M is flexible (call it $2.0M effective + site prep): easy wins on finish tier saves ~$50–100K; keep identity items intact; project lands at ~$2.05–2.15M total. This is the recommended scenario.