LOCKED — but tight strategy clear, size questionable

LDD-15 · Mechanical Room

One-line intent

Organized systems, partially revealed — the room is the project's mechanical infrastructure read as architectural feature.

Locked decisions

Zones

ZoneFunction
NorthRadiant manifold (visual wall)
SouthTanks + sink
EastElectrical + battery
CenterWorking space (service access)

Open items / engineer review

Cost drivers

Smoked glass door $2–6K · Mech room finishes $2–5K · Floor drain + sink $1.5–3K · Ventilation $0.5–1.5K. Total: $5–15K (room only; equipment in respective LDDs).

Air-gap concerns

  • 70 sqft is genuinely tight. Typical equivalent room is 80–120 sqft. Recommend bumping to ≥90 sqft (10'×9' or 12'×7.5') before structure is set.
  • HPWH in small mech room loses efficiency — vent ducts to larger space or pick different water heater.
  • Smoked glass door + visible infrastructure = real commitment. Every label/cable tie/pipe stub matters.
  • Battery code + safety implications — Powerwall/Enphase need fire separation + ventilation per code.
  • Floor drain coordination with under-slab plumbing.
  • Single mech room may be insufficient — north + south alcoves implied by 3-cluster strategy but not explicit.

Cross-references

← Inputs from

LDD-02 central manifold · LDD-05 equipment · LDD-10 middle cluster

→ Outputs to

LDD-06 local south service branch from here

Diagram

Manifold cluster locations
Mech room hosts the central manifold cluster (the largest of the three).