ROM ยฑ25% 2026 dollars ยท Mountain-West rural ยท Site prep excluded

Budget Analysis vs $1.75M

Summary โ€” Round 2 corrections in builder's favor

After two rounds of builder rebuttals, the budget gap is materially smaller. The PEMB-efficient case is now $120K over $1.75M โ€” fully closeable with easy-wins.

ScenarioTotal before site prepvs $1.75M
PEMB-efficient (builder's position)~$1.87M+$120K (7%) over โ€” closeable
Conservative ROM (reviewer's position)~$2.23M+$480K (27%) over
Low-case (favorable bids + scope discipline)~$1.70โ€“1.80Mat envelope
High-case (Delaware bid market + change orders)~$2.40โ€“2.60M+$650โ€“850K (37โ€“49%) over

Round 2 corrections (all in builder's favor)

  • IMP wall area arithmetic error โ€” `360 lf ร— 22'` = 7,920 sqft, not 14,400 sqft. IMP wall $230K โ†’ $130K. -$100K (largest single revision)
  • Kitchen vent reframed R-3 โ€” strip dedicated MUA, custom plenum, hood-specialist fee. $95K โ†’ $70K. -$25K
  • Lift reclassified material lift โ€” Asgard Press inventory, not passenger. South bay total $95K โ†’ $55K. -$30K
  • Counter tri-sectional slab โ€” three slabs at zone boundaries, no jumbo-slab premium. -$15K
  • Spine threshold formwork step-down โ€” handled at pour, no retrofit. -$1K

Site prep meaningfully de-risked. Site plan shows pier foundation, building above FEMA floodplain (FFE 252.4 vs floodplain study line 246), existing sanitary sewer lateral identified. Builder estimate ~$50K is much more credible now.

Bottom line

The $1.75M strict budget is achievable in the builder's PEMB-efficient scenario only with favorable Delaware bids + held scope discipline. Three honest paths:

  1. Trust PEMB efficiencies + grow contingency to 15% โ€” accept ~$1.85โ€“2.05M effective, treat $1.75M as the stretch target.
  2. Cut $200โ€“300K of scope โ€” see "Cost-reduction levers" below.
  3. Phase the build โ€” defer LOW finish, one ILS bay, or lift to Phase 2.

The actionable answer is to get 2โ€“3 line-item GC bids before locking the conversation.

Builder's PEMB-efficient counter-scenario (re-priced line items)

Peter argues PEMB efficiencies + concentrated finish zones reduce these lines materially:

CategoryConservativePEMB-efficientฮ”Notes
Foundation + slab (SOG w/ piers)130110-20Pier-cascade withdrawn
PEMB shell + erect220220โ€”
IMP envelope walls130115-15Arithmetic correction (was $230/$215)
Roof IMP + drainage9080-104' overhang
Spine wall + glazing11095-15
Gym hero wall + clerestory7060-10
Interior framing + drywall9565-30
HVAC (incl. boost-mode ERV)175150-25ERV upsized for kitchen MUA
Radiant + manifolds10590-15
Plumbing + fixtures115105-10
Electrical + EV + solar (30kW PV)110100-10
Lighting7065-5
Doors + stairs + finish11090-20
Kitchen + cooking + island vent7065-5Reframed R-3 (was $95/$90)
South bay (lift + equipment + workshop)5550-5Material lift (was $95/$90)
ILS finish + appliances8575-10
Flooring + threshold (LDD-24)6555-10Formwork step-down (was $70/$60)
Social counter4035-5Tri-sectional slab
Permits + design + GC fee130100-30
Subtotal~2,030~1,700-330
Contingency 10%203170-33
Project total before site prep~$2,233K~$1,870K-$363K

PEMB-efficient is $120K over $1.75M โ€” fully closeable with easy-wins ($115โ€“235K available). Conservative is $480K over. Real GC bids resolve which side is right.

Budget waterfall

Budget waterfall showing ROM cost stack vs $1.75M envelope
Original waterfall shows $2.13M; add ~$70K for Peter's LDD-24 flooring to reach ~$2.43M total.

Line-item rollup (likely case)

Category$K likely$K rangeNotes
Foundation + slab130100โ€“160Includes radiant + slab-edge insulation. Site prep excluded.
PEMB shell + erect220180โ€“2604-bay ร— 30' frame package, erection included.
Exterior envelope (IMP walls)230190โ€“2804" PVDF tier; lower tier saves $20โ€“40K.
Roof IMP + drainage9070โ€“110Separate from wall IMP.
Spine wall + glazing11080โ€“140Includes 18'ร—10' glass garage door.
Gym hero wall + clerestory7055โ€“95~190 sqft of clerestory.
Interior framing + drywall9575โ€“125Habitable-zone assemblies.
HVAC175130โ€“225Ducted + mini-splits + ERV.
Radiant + manifolds10585โ€“1353 clusters; gypcrete upstairs.
Plumbing + fixtures11590โ€“150DWV + supply + 7 toilets + 10 sinks.
Electrical + EV + solar-ready11090โ€“140400A + 2 subpanels.
Lighting (soffit + scene)7055โ€“95Linear LED + Lutron.
Doors + stairs + finish11085โ€“14530+ doors, 54" stair.
Kitchen + cooking + island vent9570โ€“130Custom integrated system.
Workshop + lift + equipment9570โ€“135Lift dominates.
ILS finish + appliances8565โ€“115Aging-in-place fixtures.
Flooring + threshold (LDD-24, new)7050โ€“95Gym urethane + SPC LVP + polished concrete + flush threshold.
Permits + design + GC fee130100โ€“170~6โ€“8% GC fee.
Subtotal hard + soft2,2051,790โ€“2,800
Contingency 10%220โ€”
Project total~2,425~$2.0Mโ€“$2.7MBefore site prep.

Cost-reduction levers

Easy wins (do these first)

MoveSavingsCost
Downgrade IMP exterior finish tier (PVDF โ†’ SMP polyester)$20โ€“40KFaster fade in 10โ€“15 years
Defer LOW finish and fixtures to Phase 2 (rough-in only)$40โ€“80KLOW unusable until Phase 2
Defer one ILS bedroom or bathroom finish$30โ€“60KLess ILS flexibility
Heat-pump water heater instead of distributed tankless$5โ€“15KSlightly less flow capacity
Vinyl LVP instead of luxury SPC$10โ€“20KFloor-feel + warranty considerations
Single washer/dryer set instead of two$5โ€“10KLess laundry capacity
Standard sectional garage doors$5โ€“10KAesthetic compromise on south face

Easy-win subtotal: $115โ€“235K. Possibly enough to close half the gap.

Harder cuts (more political)

MoveSavingsCost
Defer or eliminate lift$25โ€“55KLOW access via stair only; not aging-in-place
Standard hanging hood instead of LDD-07 integrated vent$25โ€“60KBig aesthetic compromise over kitchen
Dry climate-panel radiant upstairs instead of gypcrete$10โ€“25KWorse acoustics + slower response
Eliminate destratification fans$20โ€“35KGym comfort worse in winter
Reduce service to 300A from 400A$4โ€“8KTight on long-term capacity

Hard-cut subtotal: up to $85โ€“186K saved, but each cuts the design's identity.

Recommended path

Reviewer recommendation

  1. Confirm with the builder/owner: is $1.75M strict, or is there 10โ€“15% headroom?
  2. Get site prep from civil engineer next week. Without it, every other number floats.
  3. If $1.75M is strict and site prep is ~$50K: easy wins + defer LOW gets you to ~$2.0M before site prep โ€” still over, but much closer. The remaining $200โ€“250K gap probably means cutting an identity item or accepting a moderate overrun.
  4. If $1.75M is flexible (call it $2.0M effective + site prep): easy wins on finish tier saves ~$50โ€“100K; keep identity items intact; project lands at ~$2.05โ€“2.15M total. This is the recommended scenario.